Important monitoring projects for reservoir and diversion dams
Important monitoring projects for reservoir and diversion dams
- Performing engineering services for the third phase, including on-site and on-site supervision of the completion of the Zincheh and Kahir reservoir dam and the drinking water transmission line to 55 Kahir villages, in addition to miscellaneous works (Iranian Water Resources and Power Company)
- On-site and on-site supervision of the Kahir concrete roller dam (Iranian Water Resources and Power Company)
- On-site and on-site supervision of the Marvuk reservoir dam (Lorestan Regional Water Company)
- On-site and on-site supervision of the Tang Hamam reservoir dam (Kermanshah Regional Water Company)
- On-site and on-site supervision of the Kor city reservoir dam (Sistan and Baluchestan Regional Water Company)
- On-site and on-site supervision of the Taj Amir reservoir dam (Lorestan Regional Water Company)
- On-site and on-site supervision of the Shahid Boroujerdi reservoir dam (Lorestan Regional Water Company)
- On-site and on-site supervision of the Dasht Palang dam (Boshehr Regional Water Company)
- On-site and on-site supervision of the Zirdan dam to Pir Sohrab water transmission line, 40 km long (Water Company) Sistan and Baluchestan Regional Water Company)
- Supervisory and workshop supervision of Talvar water transmission line for 22,000 hectares of land (Zanjan Regional Water Company)
- Supervisory and workshop supervision of Gohar Kouh reservoir dam (Sistan and Baluchestan Regional Water Company)
- Supervisory and workshop supervision of Khan Abad reservoir dam (Lorestan Regional Water Company)
- Supervisory and workshop supervision of Kineh Vars reservoir dam and water transmission line (Zanjan Regional Water Company)
- Supervisory and workshop supervision of Kasyan diversion dam and water supply canals
- Supervisory and workshop supervision of Nasirabad Borujerd diversion dam and water supply canal
- Supervisory and workshop supervision of Khan Abad Dam central pumping station installations
- Supervisory and workshop supervision of Al-Shatar network pumping stations
- Supervisory and workshop supervision of Jobrast diversion dam and canal
- Supervisory and workshop supervision of Ali Abad Dorud diversion dam and water supply canals and First degree
- Supervisory and workshop supervision of the Maruk diversion dam
- Supervisory and workshop supervision, construction of the diversion dam and water transfer canal in Nasirabad, Borujerd
- Supervisory and workshop supervision of the Kasian diversion dam and water supply canals – Dasht-e-Chaghlondi – Khorramabad
- Supervisory and workshop supervision. Diversion dam and water supply canal of Darreh Dai – Aligudarz
- Supervisory and workshop supervision of the Rozbar water supply canal of Dasht Silakhor – Dorud
- Supervisory and workshop supervision of the Cheshme Par water transfer canal (Lorestan Province)
- Supervisory and workshop supervision of the improvement of the diversion dam and water transfer structures of Somar (Kermanshah Water Affairs)
- Supervisory and workshop supervision of the implementation of the Ghar (Tiron) water pumping station in Lorestan Province
- Supervisory and workshop supervision of the implementation of the Ghar (Tiron) water transfer line in Lorestan Province
- Supervisory and workshop supervision of the land equipment and renovation plan of the Zahab cooperative in Kermanshah
- Supervisory and workshop supervision of the collection of surface water in Zahedan city